Builder's Checklist
Contact: Zack Van Rossum, Building Official
Eastern District Planning Commission
285 Beech Hill Road | RR7 STN MAIN | ANTIGONISH NS B2G 2L4 | Canada
Phone: (902) 863-2366 | Fax: (902) 863-5751
www.rcbplan.ns.ca
Building > Checklist
One copy of the site plan or survey plan.
One complete set of building plans, including foundation plan, floor plan, detail section; and where applicable, plumbing schematic , electrician's application.
A completed Development Permit Application (required in ‘planned' areas) and/or Building Permit Application.
Permit Fees submitted with completed permit applications (refer to Permit Fee Schedule).
Development Permit issued (where applicable).
Department of Transportation approval (where applicable).
Department of Environment approval (where applicable).
Municipal Water and Sewer Permit (where applicable).
Building Permit issued.
Building Permit posted in a prominent on-site location.
Foundation inspection requested and completed.
Surveyor's location certificate submitted (for planned areas and areas serviced by municipal water and sewer only).
Framing inspection requested and completed.
Occupancy inspection requested and completed
Occupancy Permit issued.
This checklist provides the general process prior to and during construction. You may be advised by the building inspector of the specific requirements at the time of application.